The Chief of the U.S. Army Corps of Engineers, Lt. Gen. Todd Semonite, officially signed the Chief of Engineers Report for the San Juan Harbor Navigation Improvements Study.
The Federal Emergency Management Agency approved the extension of the U.S. Army Corps of Engineers mission assignment for emergency power restoration in Puerto Rico.
The U.S. Army Corps of Engineers (USACE) Temporary Emergency Power mission in Puerto Rico installed the 2000th power generator on Mar. 31, 2018, the agency announced.
Six months after Hurricane María made landfall, the U.S. Army Corps of Engineers “remains committed to safely and urgently restoring reliable power and returning normalcy to the U.S. citizens of Puerto Rico as quickly as possible,” the agency said on the half anniversary of the storm.
Six months after Hurricane María devastated Puerto Rico, power and water have been restored in most communities, millions of cubic yards of debris have been removed, hospitals and other government services are open and bridges are being replaced, the Federal Emergency Management Agency said.
The Puerto Rico Electric Power Authority, and the island’s energy sector as a whole, must be overhauled following the destruction caused by Hurricanes Irma and María to be more resilient and responsive to emergencies.
Fluor Corporation confirmed Thursday that it has completed work on portions of three priority 38kv power lines in large urban areas near San Juan and a fourth priority 38kv line near Caguas.
More than $870 million in federal funds has been provided to Puerto Rico survivors of Hurricanes Irma and María, the Federal Emergency Management Agency said.
The U.S. Army Corps of Engineers (USACE), Engineering and Support Center in Huntsville, Alabama, awarded a $265 million modification to an existing contract with Fluor Corp. to repair the power grid in Puerto Rico.
The U.S. Army Corps of Engineers, in coordination with the Mobile District, awarded a $93-million shared capacity contract to Power & Instrumentation Services Inc. and Ceres Caribe Inc.,
Service is an honor. It’s also an opportunity to effect change, to make progress, to develop possibilities. That’s why I’m so pleased to have joined the Department of Energy’s (DOE’s) Office of Electricity Delivery and Energy Reliability (OE).
Fluor Corporation confirmed that, working under its contract with the U.S. Army Corps of Engineers (USACE), it has completed a high priority 38kv power line near San Juan.
The Castañer Medical Hospital received the 500th generator the U.S. Army Corps of Engineers (USACE) has installed in Puerto Rico for the Federal Emergency Management Agency, it was announced.